Fort Riley Military Base
To make this project more efficient and safer, Ƶ prefabricated and skid-mounted multiple items in our fab shop for a “plug and play” application on the job site.
Southside Facility
This high-profile project consisted of two command buildings, three COFs and one hangar. P1 group used Victaulic (2 1/2” and up) and ProPress (2” and below) for 95 percent of all hydronic piping, ProPress for 95 percent of domestic water piping, and it used an Ingersoll Rand aluminum compressed air pipe system. We converted all duct to round and used Lindab “self sealing” gasketed spiral duct fittings. To make the project more efficient and safer, Ƶ prefabricated and skid-mounted all pumps and boilers along with all interconnecting pipe, valves, strainers, etc. in the company’s fab shop in Lawrence and shipped the skids to the job site and sat them in place for a “plug and play” application. Electrically, new electrical, special systems and temperature control wiring were installed for all buildings, and site lighting was added to all storage and parking lots.
Commissioning
P1 recently completed commissioning work on 34 buildings focused on energy conservations measures, BMS (controls) sequence changes, as well as mechanical repairs.
Services Provided
-
Commissioning
-
Building Technologies
-
Controls
-
Design-Build
-
Construction - Electrical, Ƶ, Plumbing and Sheet Metal
-
Fabrication - Piping, and Sheet Metal
Quick Facts
-
7 AHU’s
-
12 Condensing Boilers
-
5 Chillers with 425 Tons of Cooling
-
220 Plumbing Fixtures
Project Details
Fort Riley, KS
18 months
Need a team of professional specialty contractors to help with your next construction project? Get started by finding a P1 Construction location near you.
Still not sure if P1 Construction, LLC is the right fit? Feel free to check out more examples of our past work and hear from our statisfied customers.