Southern Hills Hospital
The initial project scope for P1 was to add one patient floor to the hospital, with upgrades to the powerhouse chiller and boilers. But multiple large change orders added significantly to the project, adding another floor as shell space along with booster pump change (original to the hospital) and new medical air and vacuum equipment.
The new medical air/ vacuum change was done live with no interruption to the hospital.
The original phasing was shown to be done in 15 phases over 24+ weeks. Working with JE Dunn, P1 helped get the work done in only four phases and in 12 weeks. The work was completed exactly on schedule with no unplanned impacts to patients, no safety issues, and no quality concerns.
Watch the progress below:
Services Provided
-
ÁñÁ«ÊÓƵ construction
-
Plumbing construction
-
Sheet metal construction
Project Details
Las Vegas, NV
April, 2024
JE Dunn